Create calculated fields in Tableau

Cal: Report Date

[Resource Date] <= [Param: Report Date]

Physical % Complete

{ FIXED [Work Package]

:

SUM(

IF [Cost Class] = ‘Earned’ AND [Cal: Report Date] = TRUE THEN [Item Cost] END

)

}

/

{ FIXED [Work Package]

:

SUM(

IF [Cost Class] = ‘Budget’ AND [Cal: Report Date] = TRUE THEN [Item Cost] END

)

}

SV by WP

{ FIXED [Work Package]

:

SUM(

IF [Cost Class] = ‘Earned’ AND [Cal: Report Date] = TRUE THEN [Item Cost] END

)

}

{ FIXED [Work Package]

:

SUM(

IF [Cost Class] = ‘Budget’ AND [Cal: Report Date] = TRUE THEN [Item Cost] END

)

}

CV by WP

{ FIXED [Work Package]

:

SUM(

IF [Cost Class] = ‘Actual’ AND [Cal: Report Date] = TRUE THEN [Item Cost] END

)

}

{ FIXED [Work Package]

:

SUM(

IF [Cost Class] = ‘Budget’ AND [Cal: Report Date] = TRUE THEN [Item Cost] END

)

}